Introduction
This week’s assignment was to do a follow-up on the
assignment from last week. The intent
was to examine the methods we used the week prior, and improve upon them to
increase the accuracy of the terrain survey.
This second report is to be more thorough and detailed, providing a
better understanding to the methods we used and a more accurate picture of what
we accomplished.
Methods
To begin this week’s assignment, we loaded our x,y, and z coordinates from last week’s data collection into an Excel file, which was then loaded into ArcMap. With the points in ArcMap, we used the 3D Analyst toolbox to create terrain maps using five different interpolation methods, and can be seen in Figures 1-5. After the terrain maps were created, we then made a 3D rendering of them using ArcScene.
After completing the terrain maps and seeing the renditions of our prior week’s effort, it was obvious our data was not even close to the accuracy required for a good terrain map. Whereas last week we used 10 cm x 10 cm grid system for our 100 cm x 230 cm flowerbed, we decided this week we would construct a 5 cm x 5 cm grid system. It was cold last week, and it was even colder this week, which caused us to seek additional processes that would decrease our time outside. One such creation was the use of a slide rule, as seen in Figure 6. On top of the cold, our flower bed terrain was also covered in substantially more snow. So, we had to do our best to create the same terrain as we had the week prior, which we believe we did relatively well. Our etch marks from last week were still present, so it did not take us long to add the 5cm increment etches and pin up the y-lines. With the grid setup complete, it was time to start collecting data.
Rather
than writing down the data points on paper and then having to type them into
excel, we decided to have one person inside on a computer entering the data
immediately. I was the lucky person to
be inside entering the points, while Amy took the x, y, and z measurements, and
Joel relayed that information to me over the phone (Figures 7 & 8).
After completing the terrain maps and seeing the renditions of our prior week’s effort, it was obvious our data was not even close to the accuracy required for a good terrain map. Whereas last week we used 10 cm x 10 cm grid system for our 100 cm x 230 cm flowerbed, we decided this week we would construct a 5 cm x 5 cm grid system. It was cold last week, and it was even colder this week, which caused us to seek additional processes that would decrease our time outside. One such creation was the use of a slide rule, as seen in Figure 6. On top of the cold, our flower bed terrain was also covered in substantially more snow. So, we had to do our best to create the same terrain as we had the week prior, which we believe we did relatively well. Our etch marks from last week were still present, so it did not take us long to add the 5cm increment etches and pin up the y-lines. With the grid setup complete, it was time to start collecting data.
Figure 6: The slide rule laying across the flowerbed, with lengths of twine making up the y-axis. Each twine is 5cm apart. |
Figure 7: Kent (myself) entering the coordinates into an Excel spreadsheet. Amy is taking the picture while her and Joel were on a short break from the cold. |
Figure 8: Amy (left) collecting the coordinates as Joel (right) relays them to me via phone. |
When
the data collection was finally complete, much to Amy and Joel’s delight, we
were able to immediately load the Excel file into ArcMap, run our preferred
interpolation method (Spline), and render it in ArcScene. Figures 9 shows the significant
increase in accuracy of the terrain map.
Discussion
Our methods during this resurvey of the terrain were
substantially improved. From the
beginning we set ourselves up better than we did last week. We made the decision that, given nature of
Wisconsin weather at this time of year, we needed to remake the terrain, setup
our grid system, and collect all of the data in a single session. This can be difficult for our group, as all
of us are both taking many courses and working at the same time. The only day that we are really able to meet
for two hours or more, outside of class, is Tuesday. Last week we made the terrain during class on
Monday, and returned on Tuesday to collect the data. As can be seen in Figure 10, rain reduced our
terrain in elevation considerable, and the frozen flowerbed made it very difficult
to dig. The use of the meter sticks as a
moveable x-axis also reduced the amount of time it would take, as we did not
need to place the 46 strands of string across the flowerbed.
Figure 10: This image is from last week's data collection day. It rained throughout the night, substantially reducing and changing the elelevation of our terrain. |
Deciding to have one person inside recording the data in
Excel as it was being collected was also an excellent decision. Last week it took me almost half an hour to
enter the 291 points into Excel, and there were a multiple errors from typing
mistakes, which required me to go back and correct them. This time we had 987 data points, and the
only issue was there were about 5 points that appeared to be missing. All I did
was take a quick look at the attribute table, went to where the points should
be, and found that I had copied the x coordinate too far down. So, those 5 points were merely shifted over 5
cm and was an easy fix.
The effect of our decision to use a 5 cm x 5 cm grid
system is even apparent in just the data points when initially added to ArcMap
(see Figures 13 & 14). Figure 15
shows the end result of our improvised methods.
Figure 11: Map export from ArcMap of our first week's data points. These were taken from a 10cm x 10cm grid system. There was a total of 291 points. |
Figure 12: Map export from ArcMap of this week's data points. These were taken from a 5cm x 5cm grid system. There was a total of 987 points. |
Conclusion
Doing this assignment a second time was an excellent learning experience. We were able to look back at what we did the week prior, improve upon our methods, and, in the end, create a significantly better map of our terrain. Not only did we learn and improve our ability to collect data, import them into ArcMap, create maps of the terrain, and create 3D renditions of them in ArcScene, but we also came together as a group.
No comments:
Post a Comment